SSC CGL Preparation – Day 7

Table of Contents

Quantitative Aptitude – Time and Work


1. Basic Concepts

  • Work: Any task to be completed.
  • Unitary Method: If A can complete work in x days, then Aโ€™s 1 day work = 1/x.

๐Ÿง  Example:

If A can do a job in 5 days, Aโ€™s 1-day work = 1/5.


2. Important Formulas

SituationFormula
Work = Time ร— Rate of workWork = Days ร— (1/Days per person)
If A can do a work in x days, B in y daysThen both in 1 day = (1/x + 1/y)
If A is โ€˜nโ€™ times efficient than BA takes 1/n of the time B takes

3. Combined Work

If A can do a work in x days and B in y days, together they will do:

  • 1 day work = 1/x + 1/y
  • Total time = xy / (x + y)

4. Work and Wages

If A and B work together and complete a work and their efficiencies are known, then:

  • Wages are divided in the ratio of work done (or efficiency ร— time worked).

5. Pipes and Cisterns

(Pipes filling or emptying tanks โ€“ same logic as Time and Work)

  • If pipe A fills tank in x hrs, 1 hour work = 1/x
  • If pipe B empties tank in y hrs, 1 hour work = -1/y
  • Net work per hour = (1/x โ€“ 1/y)

6. Alternate Days Work

If A and B work on alternate days, calculate their total work per 2 days and then determine how many such pairs fit into total work.


7. Efficiency-Based Problems

If A is twice as efficient as B, then:

  • Aโ€™s work per day = 2 units (say), Bโ€™s = 1 unit
  • Total work can be considered in efficiency units.

๐Ÿงฎ Common Shortcuts

  • Work = LCM of individual days (assume total work as LCM)
  • Use ratio method to assign work and time
  • Efficiency = 1/Time taken

๐Ÿง‘โ€๐Ÿซ Examples


Example 1:
A can do a piece of work in 10 days, B in 15 days. Working together, how long will they take?

Solution:
Aโ€™s 1-day work = 1/10, Bโ€™s = 1/15
Combined 1-day work = (1/10 + 1/15) = (3+2)/30 = 5/30 = 1/6
โ‡’ Time = 6 days


Example 2:
A is twice as efficient as B. Together they can complete a work in 12 days. How many days will A take alone?

Solution:
Let Bโ€™s 1-day work = x, so A = 2x
Combined = x + 2x = 3x
3x ร— 12 = 1 โ†’ x = 1/36
Aโ€™s 1-day work = 2/36 = 1/18
So, A alone can do the work in 18 days


Example 3:
Two pipes A and B can fill a tank in 20 min and 30 min respectively. Pipe C can empty it in 15 min. If all three are opened together, in how much time will the tank be filled?

Solution:
Aโ€™s work = 1/20, Bโ€™s = 1/30, Cโ€™s = -1/15
Net = 1/20 + 1/30 โ€“ 1/15
= (3 + 2 โ€“ 4)/60 = 1/60
โ‡’ Tank filled in 60 min


๐Ÿ“ Tips for SSC CGL

Practice Pipes & Cisterns as they are just inverse work problems.

Expect 2โ€“3 questions from this topic.

Be quick with LCM-based methods.

Understand efficiency problems deeply.

Leave a Reply

Your email address will not be published. Required fields are marked *