GyaanVibe is a focused educational platform dedicated to helping SSC CGL aspirants crack Tier 1 & Tier 2 exam with a strategic, day-wise, and well-structured preparation approach.
SSC CGL Preparation – Day 7
Quantitative Aptitude – Time and Work
1. Basic Concepts
- Work: Any task to be completed.
- Unitary Method: If A can complete work in
x
days, then Aโs 1 day work =1/x
.
๐ง Example:
If A can do a job in 5 days, Aโs 1-day work = 1/5.
2. Important Formulas
Situation | Formula |
---|---|
Work = Time ร Rate of work | Work = Days ร (1/Days per person) |
If A can do a work in x days, B in y days | Then both in 1 day = (1/x + 1/y) |
If A is โnโ times efficient than B | A takes 1/n of the time B takes |
3. Combined Work
If A can do a work in x
days and B in y
days, together they will do:
- 1 day work = 1/x + 1/y
- Total time = xy / (x + y)
4. Work and Wages
If A and B work together and complete a work and their efficiencies are known, then:
- Wages are divided in the ratio of work done (or efficiency ร time worked).
5. Pipes and Cisterns
(Pipes filling or emptying tanks โ same logic as Time and Work)
- If pipe A fills tank in x hrs, 1 hour work = 1/x
- If pipe B empties tank in y hrs, 1 hour work = -1/y
- Net work per hour = (1/x โ 1/y)
6. Alternate Days Work
If A and B work on alternate days, calculate their total work per 2 days and then determine how many such pairs fit into total work.
7. Efficiency-Based Problems
If A is twice as efficient as B, then:
- Aโs work per day = 2 units (say), Bโs = 1 unit
- Total work can be considered in efficiency units.
๐งฎ Common Shortcuts
- Work = LCM of individual days (assume total work as LCM)
- Use ratio method to assign work and time
- Efficiency = 1/Time taken
๐งโ๐ซ Examples
Example 1:
A can do a piece of work in 10 days, B in 15 days. Working together, how long will they take?
Solution:
Aโs 1-day work = 1/10, Bโs = 1/15
Combined 1-day work = (1/10 + 1/15) = (3+2)/30 = 5/30 = 1/6
โ Time = 6 days
Example 2:
A is twice as efficient as B. Together they can complete a work in 12 days. How many days will A take alone?
Solution:
Let Bโs 1-day work = x, so A = 2x
Combined = x + 2x = 3x
3x ร 12 = 1 โ x = 1/36
Aโs 1-day work = 2/36 = 1/18
So, A alone can do the work in 18 days
Example 3:
Two pipes A and B can fill a tank in 20 min and 30 min respectively. Pipe C can empty it in 15 min. If all three are opened together, in how much time will the tank be filled?
Solution:
Aโs work = 1/20, Bโs = 1/30, Cโs = -1/15
Net = 1/20 + 1/30 โ 1/15
= (3 + 2 โ 4)/60 = 1/60
โ Tank filled in 60 min
๐ Tips for SSC CGL
Practice Pipes & Cisterns as they are just inverse work problems.
Expect 2โ3 questions from this topic.
Be quick with LCM-based methods.
Understand efficiency problems deeply.