GyaanVibe is a focused educational platform dedicated to helping SSC CGL aspirants crack Tier 1 & Tier 2 exam with a strategic, day-wise, and well-structured preparation approach.
SSC CGL Preparation – Day 19
Quantitative Aptitude – Time and Work (Repeated β Advanced)
β 1. Basic Concept Recap
Time and Work problems involve calculating the amount of work, time taken, or number of workers involved in completing a task.
- Work and Time are inversely proportional.
More men = less time. More work = more time.
πΉ Basic Formulae
- Work = Time Γ Efficiency
- If A can do a piece of work in
x
days, then A’s 1 day work = 1/x - If A is βnβ times as efficient as B, then:
- Time taken by A = 1/n Γ time taken by B
- Ratio of work done in 1 day = A:B = n:1
- If A and B together can do a work in X days and A alone can do it in Y days, then:
- B’s time alone = $$\frac{XY}{Y – X}$$
- LCM Method: Assume total work = LCM of the number of days of individuals
(Useful when dealing with multiple people or machines)
β 2. Common Problem Types
πΈ A. Individual Work
“A can do a work in 10 days. How much work does he do in one day?”
β Answer: 1/10
πΈ B. Combined Work
“A can do it in 10 days, B in 15 days. How many days will they take together?”
Solution:
1-day work = 1/10 + 1/15 = $$\frac{5}{30} = \frac{1}{6}$$
β
So, total days = 6
πΈ C. ManβDay Concept
If 12 men can build a wall in 15 days, how many men are needed to do it in 10 days?
Solution:
12 Γ 15 = x Γ 10 β x = 18 men
πΈ D. Alternate Work / Replacement
A works for 5 days, then B completes the rest. Total time = ?
πΈ E. Pipes and Cisterns
- Inlet fills β +ve work
- Outlet empties β βve work
If a pipe fills in 10 min (1/10 work/min) and another empties in 15 min (β1/15),
Net 1-min work = $$\frac{1}{10} – \frac{1}{15} = \frac{1}{30}$$
β 3. Important Shortcuts
- If A can do a work in βaβ days and B in βbβ days, together:
$$\text{Work in 1 day} = \frac{1}{a} + \frac{1}{b} = \frac{a + b}{ab}$$
- Time to finish together =
$$\frac{ab}{a + b}$$
- If A is x% more efficient than B:
Let Bβs efficiency = 1, Aβs = 1 + x/100
Then A will take: $$\frac{1}{1 + x/100}$$β of Bβs time - If A and B together can do a work in X days and A alone can do it in Y days:
Then B alone = $$\frac{XY}{Y – X}$$
β 4. Example Questions
Q1. A can do a work in 10 days, B in 15 days. Working together, how many days will they take?
Solution:
1-day work = 1/10 + 1/15 = (3 + 2)/30 = 5/30 = 1/6
β
Total time = 6 days
Q2. A is 25% more efficient than B. If B alone does the work in 20 days, how much time will A take?
Solution:
Aβs efficiency = 125%, or 1.25 Γ Bβs
Aβs time = $$\frac{20}{1.25} = 16$$ days
Q3. A and B can complete a task in 12 days. B alone can complete it in 20 days. In how many days can A alone do the work?
Solution:
1-day work of A + B = 1/12,
1-day work of B = 1/20
1-day work of A = 1/12 β 1/20 = (5 β 3)/60 = 2/60 = 1/30
β
A alone takes 30 days
Q4. 8 men can complete a task in 24 days. How many men are needed to finish it in 12 days?
Solution:
Work = Men Γ Days β 8 Γ 24 = x Γ 12 β x = 16 men
Q5. A pipe fills a tank in 12 minutes. Another pipe can empty it in 20 minutes. If both are opened together, how long will the tank take to fill?
Solution:
Net work = 1/12 β 1/20 = (5 β 3)/60 = 2/60 = 1/30
β
Time = 30 minutes
β 5. SSC CGL Focused Tips
- Always assume total work = LCM when needed.
- Use the unit work method (work per day) to simplify multi-person problems.
- Time taken is inversely proportional to efficiency.
- Work = Men Γ Days Γ Hours β Useful for shift-based questions.